StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Transmission Leftovers

7/16/2023

2 Comments

 
Some things are better the second time around, like lasagna and chili.  Transmission projects, however, are not good leftovers.  Once a transmission idea is proposed to the public, vehemently contested, and eventually shelved as unneeded and impossible, it can never come back from the dead.

Or can it?

The Infrastructure Investment and Jobs Act and the Inflation Reduction Act have created a new transmission feeding frenzy from coast to coast.  Now that the government is giving away your tax dollars to provide incentive to build new transmission "for renewables," utilities and transmission developers are falling all over themselves to belly up to the buffet.  There is no actual plan for what transmission needs to be built, any transmission will do.  It's about quantity, not quality.  They just can't propose transmission fast enough.  And apparently some utilities are simply recycling old transmission projects from the last decade that were never built.

Remember the Mid-Atlantic Power Pathway, or MAPP, project?  Proposed around 2007, this hotly opposed transmission project across Maryland's eastern shore was finally abandoned several years later, citing lack of need.  The utilities behind this horrible idea were fully reimbursed for their sunk costs by ratepayers who would have "benefited" from the project.  If my memory serves, it was something like $80M that we paid for a transmission project that was never constructed.

The MAPP project is back, one of dozens of new transmission proposals currently being evaluated by grid planner PJM.  They even recycled the name... once again calling it MAPP.
Project title:  Mid-Atlantic Power Pathway (MAPP)

Project description:  Exelon is proposing a 230 mile, 500 kV AC / 400 kV DC high-voltage transmission line originating in Northern Virginia, crossing Maryland, traveling up the Delmarva Peninsula and terminating in southern New Jersey.

Do they think the folks who fought MAPP have forgotten?  It's only been 15 years.  They remember, and many are still around, with all the knowledge they gained fighting MAPP the first time.

Transmission fatigue is a thing.  Communities who have fought a transmission line are instantly opposed to another proposed for the same area, and they know what to do because they've ridden in this rodeo before.  A recent transmission proposal through New Hampshire is giving communities that fought the scrapped Northern Pass project PTSD.
When four representatives of National Grid came before Concord City Council on Monday to start the long process of expanding a power line through the state bringing electricity from HydroQuebec, they soon encountered a ghost.

“Our community still suffers from PTSD with regard to Northern Pass,” Councilor Jennifer Kretovic told them. “When you mention the words HydroQuebec, that will automatically raise concern.”

The four representatives nodded glumly.
And stupidly, I might add.  Transmission is bad enough without ghost projects adding to the hatred.

It seems that every contested and vanquished transmission project from the past 15-20 years has been resurrected.

Remember PATH, the Potomac-Appalachian Transmission Highline?  It's back.  But instead of just the revised, re-routed project that PATH finally settled on, former PATH partner FirstEnergy has proposed BOTH the original PATH route through Morgan, Berkeley and Jefferson Counties AND the revised PATH route through Frederick County, VA, southern Jefferson County, WV, Loudoun County, VA and Frederick County Maryland.  This is FirstEnergy's recent proposal for PJM's competitive transmission window.  On a map, it looks like this:
Picture
The northern line on the map is described like this:
Component title:  Fort Martin - Doubs 500 kV #1 Line

Project description: 
Construct ~158 miles of new 500 kV line from Fort Martin Substation to Doubs Substation.Terminate the new transmission line and revise relay settings at Doubs and Fort Martin substations.Install fiber OPGW along the new line route. The construction of this new line will require the acquisition of 158 miles of new right-of-way, forestry clearing, permitting, and access road construction. Re-terminate the Bismark 500 kV Line at Doubs Substation. Aerial LiDAR will be required. This new transmission line will require Proposal Components 1 (Doubs Substation - Install500 kV Breaker), 2 (Doubs Substation - Expand 500 kV), and 4 (Fort Martin Substation - Install 500kV Breaker) to be completed.

This new 500 kV line will be constructed in West Virginia, Virginia, and Maryland. Full Applications
will be required in each state. - It is assumed that the new 500 kV line will parallel existing ROW for approximately (85.6) miles and require (74.4) miles of new ROW not adjacent to existing ROW. It is assumed that no existing lines will be overbuilt with double circuit structures, but existing line rebuilds will be considered where applicable. - Approximately (695) parcels will be affected by the line route. Assumed 5% condemnation (35 parcels).

The right-of-way width is assumed to be 200 ft. This width is based on the widest ROW needed for
500 kV and does not account for structure configuration or span lengths. Widths needed may vary upon final design.

The new Fort Martin-Doubs #1 500 kV Line will be constructed on double circuit 500 kV tubular
steel monopole and two-Pole structures. The second 500 kV circuit is to be left vacant and installed at a future date. - The average span length is 1200 ft. - It is assumed that the new double circuit monopole structures will have an average height of 180 ft. Final structure heights will need to be determined during project development. FAA filing and application may be required. - The new structures will utilize custom 500 kV V-string and double I-string suspension and dead-end insulator assemblies.

This new 500 kV line provides a direct connection from the west side of the system to the east
side. - This new line provides the ability to install a second Fort Martin - Doubs 500 kV Line on the same structures, without additional right-of-way acquisition. - This new line route will provide the opportunity to loop the Fort Martin - Doubs 500 kV Line into Bedington and/or Black Oak substations in the future, if necessary for reliability or resiliency. - Greenfield construction is assumed due to outage constraints, but existing rights-of-way and corridors to rebuild lower voltage lines will be considered where applicable.
A portion of the southern line on the map from Meadow Brook to Doubs is described like this:
Component title:  Meadow Brook - Doubs 500 kV Line

Project description:  Construct 55.3 miles of new 500 kV line from Meadow Brook Substation to Doubs Substation.Terminate the new transmission line and revise relay settings at Doubs and Meadow Brook substations. Install fiber along the new line route. The construction of this new line will require the acquisition of 55.3 miles of new right-of-way, forestry clearing, permitting, and access road construction. Re-terminate the Meadow Brook - Loudon & Meadow Brook - Front Royal 500 kV lines at Meadow Brook Substation. Aerial LiDAR will be required. This new transmission line wil lrequire Proposal Components 1 (Doubs Substation - Install 500 kV Breaker), Component 2 (Doubs Substation - Expand 500 kV), and Component 3 (Meadow Brook Substation - Expand 500 kV) to be completed.

This new 500 kV line will be constructed in Virginia, West Virginia, and Maryland. Full Applications
will be required in each state. - It is assumed that the new line will parallel existing ROW for approximately (22.8) miles and require (32.5) miles of new ROW not adjacent to existing ROW. It is assumed that no existing lines will be overbuilt with double circuit structures, but existing line rebuilds will be considered where applicable. - Approximately (146) parcels will be affected by thel ine route. Assumed 5% condemnation (7 parcels).

The right-of-way width is assumed to be 200 ft. This width is based on the widest ROW needed for 500 kV and does not account for structure configuration or span lengths. Widths needed can vary upon final design.

This new line will be constructed on single circuit 500 kV tubular steel monopole structures with an
average span length of 1200 ft. - The new structures will utilize custom 500 kV V-string and double I-string suspension and dead-end insulator assemblies. - New single circuit structures will have an average height of 150 ft.

This new 500 kV Line will provide an additional and much shorter electrical path between Meadow
Brook and Doubs linking the Black Oak-Bedington corridor with the 'AP South' corridor. - Greenfield construction is assumed due to outage constraints, but existing rights-of-way and corridors to rebuild lower voltage lines will be considered where applicable.
In addition, FirstEnergy proposed building a new 50 mile greenfield transmission line from Pruntytown to Meadow Brook.

It's not an "either/or" proposition.  FirstEnergy wants to build BOTH old PATH ideas this time.

Here we go again!

Is this new transmission required to expand renewable power?  Look at the map, it's self-explanatory.  PJM is soliciting proposals to move more coal-fired electric generation from plants at Ft. Martin and Pruntytown into the Washington, D.C. suburbs.  New generation is needed there because these areas have closed a whole bunch of the "dirty" coal and gas fired generation that used to keep their lights on.  Instead of replacing what they closed with local renewables, they're burying their heads in the sand and pretending they don't need any new generation.  However, they're also building new data centers that use an enormous amount of power and leaving it up to grid planner PJM to find a way to keep the lights on and the data centers humming.  The new PATH is one proposal for PJM to do just that.  Hardly "clean and green" is it?  It's a step back 20 years in time, when PATH was proposed to move 5,000 MW of coal-fired electricity from southern West Virginia to the D.C. metro area.

So, what happens next?  PJM says it will select projects from its huge proposal list in September.  Once selected, it proposes to have the favored projects approved by its Board in December of this year.  See timeline here (these projects are in 2022 RTEP Window 3):
Picture
After being beaten into submission the first time, PATH abandoned its project and collected over $150M from electric customers like us for a project that was never built.  How much will it cost us the second time around? 

Keep your eyes on this one.  PATH did not happen the first time due to widespread opposition.  We're still here and we remember.
2 Comments

PJM's Stupendous Plan To Build New Transmission in WV, MD, VA and PA

6/16/2023

1 Comment

 
Perhaps sensing a ripe opportunity, PJM Interconnection has opened a project window to solve multiple thermal overloads in the 4-state area.  PJM says all these overloads are caused by:
  1. Proliferation of data centers in Northern Virginia that have caused increased load.
  2. Generator deactivations - i.e. closing of large baseload fossil fuel electric generators in the DC and Baltimore suburbs.
  3. Need for bulk electricity transfers from places where plants have not closed (i.e. West Virginia, Pennsylvania.)
  4. Offshore wind.
  5. New planning procedures.
A map of the overloads looks like this:
Picture
PJM's new procedures call for competitive transmission proposals.  Instead of awarding a massive project like PATH to its favored incumbent transmission owners in a smoky back room, PJM is now required to post a "problem" window to solicit possible solutions submitted by any company.  PJM publicly posts solutions without identifying who proposed them, then makes a decision on which idea best solves the problem.  Except in this instance, the problem was so large it drew solutions consisting of 72 Proposals from 10 entities, of which 7 are incumbents and 3 are non-incumbents.  16 Projects are upgrades, while 50 are Greenfield.  Greenfield means new transmission (or substations) on new rights-of-way.  There are projects proposed all over the map, from eastern Maryland to northern Virginia to southeastern Pennsylvania to eastern West Virginia.  I'm only going to concentrate on just a few for this blog.

First, here's a PJM map showing existing substations and transmission lines.  You're going to need it to follow along on the written routes.

Picture
Black Oak - Doubs Greenfield 500kV Transmission Line

The project starts at Black Oak and heads east, paralleling the existing Black Oak - Bedington corridor, for ~6 miles. The line continues east for approximately 10 miles but strays away from the existing corridor due to infrastructure build up that has occurred around the corridor in this area. The line then heads southeast where it parallels the existing Hampshire to Ridgeley 138kV corridor for
approximately 16 miles. At this point the rebuild of the existing Hampshire to Stonewall 138kV line begins. The line will be upgraded to 500/138kV double circuit. The route follows this corridor until it meets up with the Stonewall Substation. At this point the route follows the existing Stonewall to Millville 138kV line. This line will be rebuilt to 500/138kV for its entire length. After the Millville substation the route follows the Millville to Doubs 138kV transmission line. This line is rebuilt to 500/138kV until a few spans outside of the Doubs substation. The 500kV circuit diverges from the 138kV centerline and connects into the 500kV Doubs substation. 

Most high-voltage transmission projects will
require a state siting approval. To begin the siting approval process, Proposer plans to hold
pre-application meetings with the regulatory agency to introduce Proposer and the Project, as well as confirm its understanding of the process. Shortly thereafter, Proposer will simultaneously begin collecting siting data and start its outreach efforts so that public siting input is incorporated at the earliest stages of the Project. Once the Proposer identifies a preferred site/route and at least one viable alternative site/route, Proposer will carry out environmental and detailed engineering work in order to establish a highly- detailed Project plan to support the siting applications.

The project will feature a right of way width of 175 feet for the green field portion of the project. The ROW will parallel existing corridor for the first ~31 miles (the greenfield portion). For the rebuild portion, the transmission line should fit in the existing corridor, however the transmission operator may decide to expand the right-of-way.

The proposed line will cross over the Black Oak to Bedington 500kV transmission line., The proposed line will cross over the Black Oak to Junction 138kV transmission line in two locations., The proposed line will cross over the Double Tollgate to Millville 138kV transmission line., The proposed line will cross over the Hampshire to Ridgeley 138kV transmission line in three locations., The proposed line will cross over the Mt Storm to Doubs 500kV transmission line in three locations.

The preliminary design for the single circuit transmission line utilizes tubular steel monopole structures with davit arms and v-string insulators in a delta configuration. The 500kV transmission line will utilize triangular spaced triple-bundle 1272 kcmil "Bittern" ACSS/TW MA3 conductor and two optical groundwires. The preliminary design for the double circuit 500/138kV transmission line utilizes tubular steel monopole structures with davit arms and v-string insulators in a delta configuration for the 500kV circuit and davit arms and I-string insulators in a horizontal configuration for the 138kV circuit. The 500kV transmission line will utilize triangular spaced triple-bundle 1272
kcmil "Bittern" ACSS/TW MA3 conductor and the 138kV transmission line will utilize a single 1272 kcmil "Bittern" ACSS/TW MA3. The structure will contain two optical groundwires.
Check the map.  This project will cross through Jefferson County, WV and rebuild the current 138kV line to double circuit with a 500kV.  It also proposes to snake through the congested area on the mountain that PATH had so much trouble trying to find a right of way through.  It's just too narrow with many houses just outside the right of way.

Here's another... but this one is a lot more convoluted and has many different parts.  First of all, it proposes a new Bartholow substation.  It doesn't give the exact location, but wasn't PATH's ginormous substation located on Bartholows Road?  It's somewhere in the vicinity but they aren't sharing that yet.
45F1 - New Bartholow Substation - 12 terminal

AC Air Insulated Substation (AIS): New proposed 500 - 230 kV Substation. New Breaker and a Half (BAAH) 500 kV switchyard with three (3) bays, six (6) line terminals, twelve (12) 500kV, 5000A, 63kAIC Breakers, two (2) shunt 150 MVAR capacitor banks, one (1) -300 to +500 MVAR Static VAR Compensator (SVC), two (2) 500 - 230 kV transformer banks. New BAAH 230 kV switchyard with three (3) bays, six (6) line terminals, eleven (11) 230 kV, 5000A, 80 kAIC breakers.



Environmental constraints identified are manageable through implementation of an environmental avoidance, minimization, and mitigation strategy incorporated at the beginning of the routing/siting process. Co-location with existing utilities and other infrastructure was prioritized to the greatest extent practicable to minimize the environmental impact on the landscape. The proposed site crosses no national wetland inventory (NWI) wetlands or waterbodies. Fatal flaws have not been identified for proposed site. A cultural resource professional assisted with the siting process to identify and minimize impacts to known areas with historic sensitivities. An investigation to further identify and evaluate historic properties will be conducted to determine the presence of archaeologically or historically significant resources. Federally listed species have been identified with potential to occur in the area including listed bats, but no critical habitat was identified in the area of the substation site. If suitable habitat is identified or regulations change, agency coordination and species-specific surveys will occur. The project intends to adhere to tree removal seasonal restriction windows to avoid and minimize impacts to protected birds and bats, such as the northern long-eared bat, bald eagle, and other common raptors. Erosion control best management practices and setbacks will be engineered and utilized to prevent sedimentation from leaving the site for the protection of aquatic species and to avoid water quality impacts. There are no unique or sensitive environmental concerns or impacts with the proposed substation site that cannot be addressed.



The Company is committed to working with all interested stakeholders through a robust public outreach program to address/respond to community concerns and inform the public about the project to the greatest extent practicable. The Company believes a well-designed public outreach program can have numerous benefits, including fostering a cooperative relationship with landowners and other stakeholders, expediting the regulatory permitting process, and assisting with project development. In general, the purpose of the community outreach plan is to gain community support for the project. In the affected communities, the Company’s public outreach plan will educate the public and relevant stakeholders on specific project details to enable timely regulatory approvals and construction activities. Elements of the public outreach plan will include the following: 1) Identify potential issues at an early stage by engagement with key community stakeholders at the outset; 2) Broaden the community engagement process to identify potential and relevant community benefits that can facilitate community support for the proposed project; 3) Develop a broad base of community support for the proposed project before the regulatory agencies; and 4) Develop a comprehensive administrative record documenting the community outreach process that can be presented to the regulatory agency or, in the event of a legal challenge, to the appropriate court. The outreach plan proposes to dedicate considerable time and resources in engaging the community, and specifically the affected community during the planning process to identify highly sensitive areas that have the least amount of cultural, environmental, and social impacts on the community. The plans will reflect avoidance of impacts rather than mitigation. However, in some cases, if avoidance is not possible, then the Company will involve the community in providing appropriate and practical mitigation measures. The Company will commence its public outreach activities following project award.

Of course, a new substation needs new transmission lines, and there are several proposed:
40AB1 - New two single circuit 230kV transmission lines from new Bartholow substation to new Grisham substation

General route description
The route is approximately 35 miles long. The component is two single circuit 230kV transmission lines to satisfy contingency requirements with utilizing a shared tower, however the towers can be designed in such a way that they are staggered and offset as to utilize the same ROW width as a double circuit 230kV transmission line. This provides the reliability of two single circuits and the permitting and constructability requirements similar to a single double circuit tower installation. Starting at a new dead-end structure at the new Bartholow substation, the route follows the existing Doubs - Brighton 500kV transmission ROW west - southwest for almost 8 miles, expanding the existing ROW. Minor adjustments may be needed for reducing impacts to buildings and residences. The route turns south where Bennet Creek intersects with the existing Doubs - Brighton 500kV transmission ROW and then routes on the eastern side of Sugarloaf Mountain for about 12 miles before then co-locating with the existing Doubs - Goose Creek 500KV transmission ROW. The route follows the existing transmission ROW on the eastern side, expanding the existing ROW, with slight deviation at the Leesburg Water Treatment Plant to avoid impact to operations at the facility. The route shifts underground on the north side of the Potomac River at the Leesburg Water Treatment Plant to reduce viewshed issues with crossing the river and spatial constraints on the south side of the river. The lines remain underground along the Doubs - Goose Creek 500kV ROW corridor until returning to overhead construction around the southeast corner of Crosstrail Blvd and Harry Byrd Hwy. The lines follow the Harry Byrd Hwy until turning south on the east side of Loudoun County Pkwy. The lines shift to the west side of Loudoun County Pkwy near the intersection with the Washington and Old Dominion trail to avoid conflicts with the 1757 Golf Club. The lines then share a common double circuit transmission tower for remaining duration of the route as it is less than 1 mile and is advantageous to utilize a double circuit tower for cost effectiveness.

The Project is located in the valley south of the Potomac River in Loudon County, traversing north through Montgomery and Frederick Counties in Maryland. A former agricultural region, Loudon County is now densely developed with commercial buildings and planned residential communities within commuting distance to Washington, D.C. Some industrial facilities are located to the south of the project area. Slopes are gentle, approximately 4%. The project terminates on the north side of the Potomac River in Frederick, Maryland where the topography is generally rolling. Elevations range from a low of near sea level along the Potomac River to about 875 feet. The river valley’s topography includes little steep terrain, but some steep gradients do exist adjacent to the river. These land elevations and the degree of slope have influenced land use in the watershed. The region’s relatively flat topography has made it easily accessible for development and agriculture in some areas next to the river and its tributaries.
The new right of way will have its own corridor for approximately 60% of the route length. The right of way will be an expansion of an existing transmission line corridor for approximately 35% of the route length. The right of way width will be 60 feet and it will accommodate 2-230kV lines. Approximately 5% of the route will be underground in narrower and congested areas where overhead construction was considered not feasible. Where underground transmission line segments are not sited by permits issued by the Authority Having Jurisdiction, a 40 ft wide right of way would be required for construction.

The proposed structures for each of the two proposed lines will be single circuit 230kV steel monopoles (TVVS-230) in a vertical conductor configuration. Any proposed dead-end structure will be a steel monopole. The portion of the route proposed to be underground will utilize duct bank construction with 3-cables per phase and splicing vaults at regular intervals.

43e - New 230kV transmission line from new Bartholow substation to existing Mt. Airy substation

The route is approximately 5 miles long. Starting a new deadend structure at the new Bartholow substation, the line routes northeast along the northside of the existing Conastone to Brighton 500kV transmission ROW. The line follows the existing ROW for about 4.25 miles before turning north, routing to the Mt Airy substation and then terminating at the substation.

The project is located in the Piedmont Upland portion of Maryland’s Frederick County. The Frederick Valley, through which the Monocacy flows, is nestled between the Catoctin Mountains to the west, and the lower Parrs Ridge to the east. The river valley’s topography includes little steep terrain, but some steep gradients do exist adjacent to the river. These land elevations and the degree of slope have influenced land use in the watershed. This section is underlain by metamorphic, igneous, and sedimentary materials, related to volcanic activity that occurred in Precambrian time. The region is comprised of rolling upland with herringbone texture and underlain with siltstones and quartzites.

The new right of way will be an expansion of an existing transmission line corridor for approximately 90% of the route length. The right of way will have its own corridor for approximately 10% of the route length. For approximately 1 mile, the right of way width will be 45 ft, for approximately 3.3 miles, the right of way will be 60 ft and will accommodate a portion of component 47ad within it. For approximately 0.5 miles the right of way will be 40 ft wide.
The majority, approximately 80% of the proposed structures will be single circuit 230kV steel monopoles (TVVS-230) in a vertical conductor configuration. Approximately 20% of the structures will be double circuit 230kV steel monopoles (TVVS-230DC) in a vertical conductor configuration. Any proposed dead-end structure will be a steel monopole.

47abc - New 500kV transmission line from new Goram substation to new Bartholow substation

The route is approximately 61 miles long. Starting a new dead end structure at the new Bartholow substation, the line routes northeast along the north side of the existing Brighton to Conastone 500kV transmission ROW. The line follows the existing ROW for about 49 miles and then turns north where the Otter Creek to Conastone 230kV transmission ROW coincides with the Conastone to Brighton 500kV transmission ROW. The line then follows along the west side of the Conastone to Otter Creek 230kV transmission ROW until it reaches the new Goram substation where it terminates.

The project is located in Maryland’s Frederick, Carroll and Baltimroe counties east of the Monocacy River. The Frederick Valley, through which the Monocacy flows, is nestled between the Catoctin Mountains to the west, and the lower Parrs Ridge to the east. The river valley’s topography includes little steep terrain, but some steep gradients do exist adjacent to the river. These land elevations and the degree of slope have influenced land use in the watershed. The region’s relatively flat topography has made it easily accessible for development and agriculture in some areas next to the river and its tributaries. The project continues north into the Piedmone Upland area of York County, Pennsylvania, characterized by rolling hills and valleys, generally with gentle to moderately steep slopes. However, steeper slopes with narrow valley bottoms dominate near the Susquehanna River. Many higher ridges are underlain by more resistant bedrock such as quartzite. This Section was formed by fluvial erosion and some peri-glacial wasting and averages about 600-700 feet in elevation. The drainage pattern of the area is considered to be dendritic. Slopes in the range of 0-8% are common throughout York County.

The proposed structures will be single circuit 500kV steel monopoles (TVVS-500) in a vertical delta configuration. Any proposed deadend structure will either be a 3-pole, one phase per pole configuration.

There may be more we haven't found yet.  PJM's plan is to review the submitted proposals and provide more updates at the July TEAC meeting.  PJM is targeting Dec 2023 Board Approval – Oct and Nov TEAC 1st and 2nd reads.  Hopefully PJM will provide a full list at the July meeting, along with its preliminary evaluation and ranking of proposed projects.  None of these ideas have been accepted and ordered by PJM yet, but... get ready... they could be.

It's been really quiet in our area since PATH died but now the push is on nationally to double or triple the amount of transmission built.  For every transmission line you see now, there will be two new ones.  That's a lot of transmission!  And if you haven't been following along for the past decade (the Post-PATH era of peaceful rebuilds and upgrades) there are many new laws and policies that will come into play this time around.  Just to name one... Congress gave FERC the authority to site and permit new transmission located in a National Interest Transmission Corridor (NIETC) in the event that a state denied a permit.   Getting a NIETC is easier than ever now.  The U.S. DOE will be handing them out like candy to any transmission developer that requests one.

Let's hope PJM remembers the black eye we gave the last transmission proposal that attempted to site here and moves on to other pastures.  We've also expanded our opposition team by connecting with other groups that successfully fought proposed transmission lines on the eastern half of the map and don't want to see more.  It's going to be the motherlode of opposition.

For now, keep your fingers crossed... and get reacquainted with your opposition self.  It's coming.

1 Comment

The Blackouts Are Coming!  The Blackouts Are Coming!

3/2/2023

0 Comments

 
Picture
It seems not even Paul Revere could alert our biased mainstream media to cover a recent paper from PJM Interconnection that reports major grid reliability problems on the horizon if we continue down our current path toward the Emerald City of Green Energy and Unicorn Farts.

When the biggest electric grid operator in the country reports
For the first time in recent history, PJM could face decreasing reserve margins should these trends – high load growth, increasing rates of generator retirements, and slower entry of new resources – continue. The amount of generation retirements appears to be more certain than the timely arrival of replacement generation resources, given that the quantity of retirements is codified in various policy objectives, while the impacts to the pace of new entry of the Inflation Reduction Act, post-pandemic supply chain issues, and other externalities are still not fully understood.
What this means is that big energy generators that can run any time they are needed are being shut down and they are not being replaced with new generators that can keep up with demand.  Eventually, this hot potato is going to land and the lights are going to go out.

Maintaining an adequate level of generation resources, with the right operational and physical characteristics, is essential for PJM’s ability to serve electrical demand through the energy transition.
Our research highlights four trends below that we believe, in combination, present increasing reliability risks during the transition, due to a potential timing mismatch between resource retirements, load growth and the pace of new generation entry under a possible “low new entry” scenario:

The growth rate of electricity demand is likely to continue to increase from electrification coupled with the proliferation of high-demand data centers in the region.

Thermal generators are retiring at a rapid pace due to government and private sector policies as well as economics.

Retirements are at risk of outpacing the construction of new resources, due to a combination of industry forces, including siting and supply chain, whose long-term impacts are not fully known.

PJM’s interconnection queue is composed primarily of intermittent and limited-duration resources. Given the operating characteristics of these resources, we need multiple megawatts of these resources to replace 1 MW of thermal generation.
Well, thanks a lot, policy makers!  Electricity is soon going to be a commodity only for the moneyed elite, coincidentally the same people who have created this certain Armageddon.

And the only people interested in reporting this clarion call of impending doom were bloggers, trade press, and media outlets designated biased and unacceptable.  Where were the mainstream media?  They were too busy pretending that a whole bunch of new transmission would allow regions like PJM to "borrow" power from neighboring regions to keep the lights on.  Except those regions are also struggling with the same issues and were expecting to borrow from PJM.  Or maybe they were making up stories about how the grid is failing.  Or that the weather is getting worse.  Or that we need lots more wind and solar to stop climate change.  Or maybe there are too many plastic straws?

What happens when the blackouts start?  We almost had one in PJM on Christmas Eve.  And because we were short on generation here, and the Tennessee Valley Authority could not borrow from us, they actually DID have blackouts.  And still the policy idiots who have never even seen PJM's control room, much less talked to the heroes who work there, blathered on about needing more wind + solar + batteries + transmission.  My eyes are wide open and I'm seeing that the independent entities whose responsibility is keeping the lights on are increasingly concerned that we're on the path to disaster.  In this day of cancel culture, many walk on egg shells to issue a warning without ending up fired, with 100 filthy protestors littering in their front yard and preventing their neighbors from sleeping.

It's real.  It's happening.  Faster and faster and faster every day.  We are retiring too much fossil fuel generation and not replacing it with anything.  Let's hope it doesn't damage the grid and plunge us into months or years of darkness before these idiots wake up.

The blackouts are coming!
0 Comments

New Jersey Wants Other States to Pay for its Environmental Laws

10/5/2022

0 Comments

 
As Gomer Pyle used to say:
RTO Insider reports:
New Jersey officials hope to engage in “horse trading” with other PJM states over the cost allocation of transmission needed to meet their climate goals, a key state regulator said last week.

“The other clean energy states and PJM are looking at billions of dollars of transmission upgrades if we do it the way we’re doing it now, when we can meet all the needs of the entire PJM region at approximately the same price,” he said. “So there’s a lot of room for horse trading, if we can get the parties to the table.”

The SAA leaves New Jersey “almost in a hostage situation at the moment,” Silverman said. “The transmission projects that we are planning benefit many states in PJM; they will see lower production costs as a result of these upgrades. But because of the way the system works, we are solely responsible for the cost. That needs to change.”

Oh, please, you're a hostage of your own actions, New Jersey!

New Jersey asked PJM to solicit transmission proposals that would support offshore wind under PJM's "State Agreement Approach" that allows a state to put new transmission in PJM's plan, but only if they agree to pay for it.  ALL OF IT.  One hundred percent!

But now that New Jersey has "estimated costs would be $5 billion to $34 billion" it suddenly wants other states to pay for some of it because they may receive some fake "production cost" benefits that they never asked for and don't need (if they did, PJM would plan a transmission line outside the SAA).

Benefits are not "benefits" when you don't need them.  It's like charging you for a dessert you don't want or need, but it looks good on the table and you might just take a bite.

So, what do you think?  Did New Jersey honestly intend to pay for these offshore wind lines itself before it found out how expensive it was going to be, or was it just pretending all along?  Did New Jersey think that it could influence other states to take a bite once the dessert was on the table?

Sneaky, sneaky, but I'm sure some PJM states won't have any problem at all saying "no" and letting New Jersey pay for its own legislative boondoggles.

0 Comments

Groundhog Day!  Transource is Back!

9/24/2022

0 Comments

 
Thought you were done with the Transource Independence Energy Connection when the Pennsylvania PUC denied their application to permit the project?  Thought you were done with it when Transource lost its appeal in the Commonwealth Court?

Sorry.  Even though that case has not quite exhausted its appeal in the U.S. District Court for the Middle District of Pennsylvania, and even though PJM suspended the project and removed it from its planning models, Transource has chucked that plan and resubmitted the same project in PJM's July 2022 competitive proposal window to solicit project proposals to address numerous reliability criteria violations on several flowgates in Maryland, Virginia, and Pennsylvania.

You can see Transource's new (old) proposal here. (Click to expand 2022 RTEP Window 1 at the top of the list.)  It's project number 633.  Transource describes its new proposal as:
This Proposed Solution is a resubmittal of the modified Independence Energy Connection (IEC) Project. The Proposed Solution consists of: (1) the IEC West Portion, which is comprised of approximately 29 miles of new double-circuit 230 kV AC overhead transmission line between the existing Potomac Edison Ringgold Substation in Washington County, Maryland to a new Rice Substation in Franklin County, Pennsylvania; and (2) the reconfigured IEC East Portion, which is primarily comprised of adding 230 kV AC overhead transmission lines between a new Furnace Run Substation in York County, Pennsylvania, and the existing BGE Conastone (via Baltimore County) and Graceton Substations in Harford County, Maryland.
That's right... Transource has taken its old project and resubmitted it to solve new "reliability" needs.

It's Groundhog Day!

It's not like Transource didn't already try to morph the IEC into a "reliability" project after the economic need for it evaporated during the PA PUC evidentiary hearing.  They tried really hard to find new reasons to build the same old, tired project without having to start again.  But the PA PUC rejected the idea that it could substitute a new "need" for the old one without PJM going through the whole planning cycle to determine if IEC was a good solution for the small reliability issues that may arise in the future. 

The jury is still out on that one.  When PJM suspended IEC, it noted:
Violations are small in magnitude and operating steps for a short term duration can mitigate issues pending further review in 2022 RTEP.
And now here we are... in the 2022 RTEP, where PJM has opened a competitive window for projects that would solve those "small in magnitude" reliability violations.  Transource still has to be selected as the best project submitted in the window, and approved by the PJM Board of Managers, and that hasn't happened yet.  There are plenty of other projects that have also been submitted.  Some projects are cheaper, some projects ar less invasive, some projects are more likely.  Transource's chances here are not great, but it bears watching.

Why would PJM waste another 7 years on a project that has already been rejected by a state utility commission?  And what if Transource wins its federal court appeal and the denial is remanded to the PUC?  Does that mean Transource will build the same project twice?  Seems like the more logical solution for PJM is to go with a new and different project without all IEC's baggage.  But when has PJM ever done anything logical when selecting projects?  Transource has already poured tens of millions into the IEC, and ratepayers are on the hook to pay for it, whether it is ever built or not, thanks to recovery guarantees granted by the Federal Energy Regulatory Commission.  Why would PJM encourage dumping more ratepayer money into the black hole of a project that is unlikely to ever be approved and built?  And why would PJM select a project with entrenched opposition, knowing that it would be hotly opposed from Day 1?

It seems that the good citizens of Pennsylvania and Maryland may never be free of the Transource IEC if the company keeps resubmitting the same project over and over, like a monkey flinging poop on the wall to see what sticks.  Nothing is going to stick, but it doesn't keep Transource from trying.  After all, ratepayers are on the hook for all the costs of Transource's Ground Hog Day project.

The least they could have done is rename it this time around.  How does Transource Groundhog Day Project sound?
0 Comments

Electric Hot Potato

8/2/2022

0 Comments

 
Picture
The U.S. electric grid is divided up into different regions, and several regions are struggling to keep the lights on this summer due to lack of generation at peak demand times.  There are issues in the Midwest, and Texas, and much of the west.  Clean energy fanatics like to blame this on "climate change" and pretend that "extreme weather" is to blame.  They keep advocating for more wind and solar generators and new transmission lines to connect them.  They make all sorts of suggestions about how we can avoid overtaxing renewable energy generators that may fail to operate when energy is needed.  The latest seems to be that air conditioning is overtaxing the system and we should learn to live without it, like our ancestors did.  What's next?  Heat?  Should we all switch to fireplaces and wood stoves and remove all our indoor plumbing so it doesn't freeze in the winter?  Worst of all, they call this "progress."

The wind and solar fantasy asserts that if we only triple the amount of electric transmission in this country, we'll have the capacity to ship every electron generated anywhere in the country to any other place that needs electricity.  The idea is that we can "borrow" from our neighboring regions when our own is deficient.

But let's pull back the wrapper on that idea a bit, shall we?  The PJM Interconnection region consists of Mid-Atlantic states and pushes west into parts of Illinois.  It covers the Ohio Valley, where the bulk of the electricity to fuel the East coast has been produced for decades at "mine mouth" plants that burn coal and natural gas and then ship the electricity east on gigantic transmission lines.  Because PJM is fossil fuel heavy (60% of the power in PJM is produced by coal and gas), it is a favorite place to "borrow" power when wind and solar is not producing enough in neighboring regions that have overbuilt wind and solar and closed their own coal and gas plants.

But now PJM is on the verge of its own crisis.  Where will PJM "borrow" power from when the surrounding regions don't have enough to share, and in fact are trying to "borrow" from PJM?  A group of power suppliers in PJM are speaking out about the upcoming crisis:
On the supply side in PJM, "we're seeing dramatic retirements" of coal-fired generation, with PJM retiring about 15 GW of coal in the next two years that it is not being replaced on a one-to-one basis, Thomas said.
The Midcontinent System Operator is experiencing a similar trend, with incremental generation resources being added that do not have the same reliability attributes as those being retired. "They are adding megawatts that are less valuable than the megawatts being retired, meaning they need to add significant multiples to replace what's being retired," he said.
In MISO, the accredited capacity being added goes down out to 2041, while the future load scenarios continue to go up.
The generator group calls this a "house of cards."  I've been referring to it as a game of hot potato.  Whatever its name, it means that we will run out of places to get power from very soon.  Are you ready to do without?
"This is kind of a fascinating trend, and arguably not a sustainable trend, because what all these other regions are counting on is importing power from other areas of the country to make up the difference and that's a house of cards waiting to fall," Thomas said.
PJM is not one of the areas identified by the North American Electricity Reliability Corporation, an international regulatory authority, as having reliability concerns, but "they're coming in a big way," he said.
The PJM interconnection queue of resources planning to connect to the grid is 95%, if not more, wind and solar power resources, which is where the economic signals are right now.
"There is going to be very little to no new natural gas coming into the system and coal is going to continue to retire" with the nuclear power resources remaining because they are subsidized at the state and federal level, Thomas said.
So we're retiring the reliable fossil fuel resources we (and other regions) have depended on to keep the lights on, and replacing them with intermittent, weather-dependent renewables that are not reliable.  And our government keeps propping up intermittent renewables with tax credits, loans and a plethora of expensive programs and regulations that make them a financial gold mine for companies that construct them.
One of the core tenets of the PJM capacity market is that in order to have capacity it must be deliverable. A megawatt of power on the system only has value if it can be delivered at peak demand periods, Thomas said.
PJM has been giving capacity accreditation to intermittent resources above their approved capacity injection rights levels, so these resources were selling capacity that was not deliverable, and that is a problem, he said.

The problematic aspect is consumers have been paying for capacity that has no value at peak, and suppliers "are getting boxed out of the market by these undeliverable megawatts," Thomas said.

Government spending is making our grid unreliable.  Can we change course before the lights go out?
0 Comments

Dropping Off Some Reality

7/17/2022

0 Comments

 
Picture
Some of Invenergy's fake news this past week mentioned that Grain Belt Express will "drop off" power in Missouri.  This is an inapt phrase used by people who don't understand transmission.  It annoys the spit out of me.

When you think "drop off" it sort of sounds like Missouri is getting a gift of electricity.  But it's actually more like getting a delivery of something you ordered and paid for, like a box of Amazon junk.  Did anyone in Missouri order electricity from Invenergy?  If the answer is "no", then you're not getting anything.  Only someone who has ordered and paid for the merchandise (electricity) is going to have it "dropped off" in Missouri.  There's no such thing as a free lunch.

Our electric transmission system is sort of like a network of water pipes.  That network is fully pressurized with water, and only when a paying customer turns on the taps do they receive anything.  Electricity is like water in a pipe network.  The lines are fully pressurized with electricity.  Only when you've signed a contract to pay for the electricity and for the delivery do you get to turn on a light switch and receive electricity from Grain Belt Express.

The problem is that GBE has only one known customer, a common buyer for municipal electric distributors known as MJMEUC.  MJMEUC signed a contract to purchase "up to" 250 MW of transmission service on GBE.  Separately, it signed a contract with a wind generator in Kansas to buy electricity to be delivered on GBE.  Only those customers who take service from MJMEUC will receive anything from GBE.  The rest of Missouri gets nothing.

The only thing being "dropped off" in Missouri is propaganda.

And think about this...  MJMEUC's contract buys electricity shipped to Missouri on GBE, but it also buys service for MJMEUC to ship electricity from Missouri to PJM in equal amount.  Now go back to that analogy about the water pipe network... if MJMEUC buys electricity and sells electricity in equal amount, is there really any electricity being "dropped off" in Missouri at all?  Electrons are all the same, no matter where or how they are generated.  The electrons from Kansas are exactly the same as the ones generated in Missouri.  MJMEUC actually gets nothing but the bill for pretending it's buying and selling electricity.  If the price MJMEUC buys electricity for in Kansas is less than the price it sells that electricity for in PJM, then MJMEUC gets paid the difference, minus line loss that happens from being transmitted and converted from AC/DC/AC.  Is it worth it?  Would PJM want to buy power from Missouri when it can generate the same power at home?

But what if the second "phase" of GBE from Missouri to PJM is never built and MJMEUC can't sell electricity, what does MJMEUC get then?  It gets more electricity than it needs to serve load and the generators in Missouri could be shut down.

It sort of sounds like the biggest scam ever, doesn't it?

I sort of wish these folks would educate themselves about the physics of electricity and the realities of the electric power market.  Then they'd simply drop Grain Belt Express off the nearest cliff.

Look out below!!!
0 Comments

Transource Loses Appeal

5/5/2022

0 Comments

 
Picture
The Commonwealth Court of Pennsylvania has denied Transource's appeal of the Pennsylvania Utility Commission's denial of its siting application.
Because we conclude that the Commission’s decision denying the Siting Applications and rescinding Transource’s provisional CPC was in accordance with Pennsylvania law, including Sections 1501 and 2805(a) of the Code, and Section 57.76(a) of the Regulations, and is supported by substantial, credited evidence
of
record, we affirm.
In plain language, this means that Transource loses and the PUC's rejection of the Transource project stands.  Congratulations, folks!

However, Transource's suit in the United States District Court for the Middle District of Pennsylvania is still alive, but it is now more unlikely than ever that Transource will prevail.  Transource's argument there is that PJM determines when transmission lines are needed and the state's only role is to decide where to put it.  That argument has never made sense, and makes even less sense now.  Here's why:
As for Transource’s arguments that PJM’s determination of need would be binding due to this matter involving issues of interstate regional transmission subject to FERC oversight,the ALJ held that the Commission was obligated to make an independent determination based on Pennsylvania law. (Id.at 82, 86, 99-102.)The ALJ further observed that while FERC has exclusive jurisdiction over the interstate transmission of electric energy and wholesale electric process, that jurisdiction was limited to matters that are not subject to state regulation. (Id.at 85 (citing Section 824(a) of the Federal Power Act, 16 U.S.C. § 824(a)).) According to the ALJ, FERC recognized this limitation by stating that there is “longstanding state authority over certain matters that are relevant to transmission planning and expansion, such as matters relevant to siting, permitting, and construction” and that the FERC was in noway invoking “an exercise of authority over those specific substantive matters traditionally reserved to the states . . . .”(Id.(quoting Transmission Planning and Cost Allocation by Transmission Owning & Operating Pub.Utils., 76 Fed. Reg. ¶¶49,842, 49,861 (Aug. 11, 2011) (FERC Order No. 1000)).) This means, according to the ALJ, that FERC Order No. 1000 was “not intended to dictate substantive outcomes” or to allow FERC to “determine what needs to be built, where it needs to be built, and who needs to build it.” (Id.at 85 n.13 (quoting S.C. Pub. Serv. Auth. v. Fed. Energy Reg. Comm’n, 762 F.3d 41, 57-58 (D.C. Cir. 2014) (internal quotation marks and citation omitted)).)
The PUC's decision was in accord with state law.  PJM has no authority when it comes to siting and permitting.  End of story.  If Transource was smart, it would withdraw the federal petition and run as fast as it could go back to Ohio.  But it probably won't.
What an astonishing waste of hundreds of millions of dollars that electric customers will be paying back (plus interest) in their monthly electric bills for years to come.

Here's something interesting from the Court's Opinion:

As for the resolution of congestion in the APSRI, it does not appear that we have ever held that congestion, which is an economic consideration, is sufficient on its own to support need or necessity under Pennsylvania law.
This "congestion relief" project was doomed from the start.  Relieving congestion is not "need" in the same realm as reliability concerns.  PJM should think long and hard before trying this again.  PJM should take the advice of its Market Monitor and revise its market efficiency project process to produce fair and accurate results that can withstand the test of time.  The Court said
It was not just OCA’s witness who criticized PJM’s cost-benefit analysis, but PJM’s own Independent Market Monitor who suggested that its market efficiency process, which includes the cost-benefit analysis, be reevaluated and that the actual costs and benefits of a project should be considered and not ignored in determining whether a market efficiency project is needed.
The "need" for this project began to evaporate before it was even ordered.  Congestion is an ever-shifting economic concept that cannot be used as the basis for a transmission project that will take years to approve, permit, and construct.

Bravo to the PA Office of the Consumer Advocate for all its hard work to protect Pennsylvania consumers and for supplying the evidence that demonstrated how flawed PJM's market efficiency process actually was.

Many concerned citizens felt that PJM was lying about the project and its cost benefit analysis.  In the end, the truth was revealed.  How could anyone ever trust PJM's magic math findings that new transmission is needed ever again?
0 Comments

PJM Suspends Transource Independence Energy Connection Project

10/7/2021

0 Comments

 
A couple weeks ago, PJM's Board of Managers very quietly suspended the Transource Independence Energy Connection Project "due to permitting risks."*

Between court, writing regulatory filings, and *gasp* a long-delayed vacation, I totally missed it.  From the look of things, though, so did everyone else.  So it's time to stand up and cheer, everyone!  You did it!!!

What does "suspend" mean?  It means that the project, which PJM calls "9A", has been removed from PJM's Regional Transmission Expansion Plan "pending further notice."  The project is not outright cancelled in its entirety... yet.  But, this means we're half-way there!!!
PJM says it will remove 9A from its upcoming RTEP and re-evaluate any reliability issues that remain.
Picture
And what reliability issues does PJM foresee in its unneeded project crystal ball?  These. 
Picture
But, pay attention to that last sentence in the very small font.  "Note: Violations are small in magnitude and operating steps for a short term duration can mitigate issues pending further review in 2022 RTEP."

Violations are small and not causing any problems currently.  You probably don't need a $500M sledgehammer to crack these nuts.

However, this whole thing bears watching.  I hate to tell you this, but when the same thing happened with the PATH Project, we had to wait 18 months for the re-evaluation and the actual cancellation of the project.  But I fully expect it is coming.

Now maybe Transource can quit wasting my money?
*This means YOU!  Good work!
0 Comments

Transource Embarks on Fool's Errand to Appeal PA PUC Decision

6/30/2021

0 Comments

 
Transource filed its big and bad federal appeal of the Pennsylvania PUC's denial of its transmission permit application last week.  Finally got around to reading it.  It's uninspired, bleary, legal dreck that relies on generalized federal statutes and bogus claims of Constitutional violations by the PUC.  Really?   Transource is using my ratepayer dollars to pay someone to write this garbage?

Transource presents the limitations on federal authority over state transmission permits, but tries to pretend there is some federal authority possessed by FERC that neuters state authority. 
Although the Federal Power Act assigns
authority over regional transmission projects and interstate transmission needs to
FERC, it preserves state authority over siting and construction issues related to those
projects. See New York, 535 U.S. at 18-22 (explaining that 16 U.S.C. § 824 contains a
“‘clear and specific grant of jurisdiction’ to FERC” over interstate transmission service
and rates but “reserve[s] state powers” over other matters); S.C. Pub. Serv. Auth., 762
F.3d at 62
Transmission rates and transmission planning -- that's the only thing under FERC's jurisdiction.  Permitting is handled by the states.  Transource thinks it's so crafty pulling the wool over the Court's eyes by attempting to equate rate authority with permitting authority.  The PA PUC did not attempt to interfere with transmission RATES as prohibited under Nantahala Power & Light Co.  What kind of a dolt wrote this crap?  FERC's planning authority does not extend to or overrule state permitting authority.  It's pretty simple!

Transource thinks that state authority over transmission permitting is a narrow left over from things the Feds don't want to cover. 
Transource brought its exceptions to the Recommended Decision before the full PAPUC, explaining in detail how the Recommended Decision misinterpreted FERC’s Order No. 1000, the meaning and weight of the PJM regional transmission planning process and decision on Project 9A, and the remaining role left for the PAPUC under state law in this context.
Sorry, Transource, federal law says transmission siting and permitting are left to the states.  Their jurisdiction is broad.

Transource also thinks that by participating in PJM's regional transmission world Pennsylvania is subjecting itself to PJM's authority over all things electrical.  If this is true, states are going to check out and begin to run their own systems on a state level.  Is this what FERC and PJM want?
Pennsylvania made the choice to allow its utilities to join PJM, and it has reaped the benefits of being part of an integrated regional market. A consequence, however, is that the state has chosen to subordinate its police power interests in determining the need for new transmission projects to PJM’s determination of regional needs.
RIDICULOUS!

Transource also attempts to put the onus on the PA PUC to take some action at PJM's committee meetings, or by filing a complaint at FERC, if it disagreed with PJM's "need" determination.  The PA PUC is not a subservient creature under PJM's thumb.  PJM's designated entity brings a project to the PUC, and the PUC decides, not the other way around.  Ya know, PJM's little book of rules allows a Designated Entity to get off the hook for constructing a project when a state fails to approve.  That pretty much tells you all you need to know about the authority of states to have the final say on transmission permits.

Transource pretends it is still building the project, and that it needs to access people's private property for its tests and studies.
Under Pennsylvania law, the PAPUC’s order had immediate effect and is in force today, see 66 Pa. Cons. Stat. § 316, meaning that Transource is no longer a Pennsylvania-authorized public utility. Thus, Transource is no longer authorized to access lands for project assessment or to conduct appraisals.
Yes.

Transource also worries that PJM might cancel its project if the court doesn't hurry up and overturn the PUC.
Transource PA faces the prospect of imminent and irreparable harm as a result of the PAPUC’s order. Under its Designated Entity Agreement, Transource PA is required to acquire all state permits by September 30, 2021. A failure to meet that milestone date constitutes a breach of the agreement, which could result in the elimination of Project 9A from the Regional Transmission Expansion Plan and the termination of the agreement.
Poor, poor Transource!  What a victim!  So, who is in charge of PJM transmission projects again?  Is it PJM?  Or is it Transource?  Seems like cancellation would be a blessing for all involved.... except it doesn't make money for AEP!

Speaking of victims... Transource is quite worried that the costs of this appeal could end up coming out of the pockets of regional ratepayers... like the other $100M or so Transource has already wasted on this project without care or consideration.
Transource PA requests such other and further relief as the Court may deem just and proper, including attorneys’ fees pursuant to 42 U.S.C.
§ 1988.
Transource acts like the legal fees are coming out of its own pockets.  It isn't intending to pocket reimbursement for legal fees, and charge ratepayers for them anyhow, is it?  Someone had better check...

Transource makes much of PJM's "congestion" determinations and cost/benefit calculations.  PJM simply wasn't believable to the PUC, who has a duty to examine the evidence and find facts upon which to base its decision. 

The "congestion" PJM initially found has pretty much entirely disappeared today.  PJM did not disagree with that, it simply told the PUC that it should base its current decision on PJM's stopped clock analysis circa 2015.  Same with the cost/benefit analysis, which was created using PJM's Magic Math Calculator.
Picture
There's simply nothing in Pennsylvania state law that controls the actions of the PUC that requires the PUC to ignore evidence that contradicts PJM.  And, of course, there's absolutely nothing in federal law either.

Transource fails to point to any federal law that was violated by the PUC, and its claims of Constitutional violations are overblown nonsense that fail to acknowledge ALL the reasons the PUC denied Transource's application.
Bottom line:  There is nothing in state or federal law that gives authority to issue or compel state transmission permits to an unelected, unappointed cartel like PJM.  Pennsylvania law is the only law that matters here, and that law requires the PUC to determine whether the project is needed.  It does not require that the PUC accept need determinations made by entities outside state control.

End of story.
0 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.